BANGOR – October 9, 2026 – From October 16 to October 19, the Maine Department of Transportation will perform work on the I-95 bridges over Broadway at Exit 185 in Bangor as part of the ongoing I-95 bridge replacement project.
Crews will complete shoulder reconstruction, milling, paving, and related work on I-95 Southbound necessary to transition traffic from the temporary southbound bridge onto the new, permanent, southbound bridge.
The work will proceed in four phases, with lane and ramp availability changing as construction progresses:
- Phase 1: The southbound high-speed lane will be closed to traffic while crews complete milling and paving at both ends of that lane. The southbound travel lane will remain open across the temporary bridge, and both the southbound on-ramp and off-ramp will remain open.
- Phase 2: The southbound high-speed lane will be opened to traffic across the new bridge. The southbound travel lane and the Exit 185 southbound off-ramp will be closed while crews complete excavation, milling, and paving at the north end of the travel lane and ramp.
- Phase 3: The southbound high-speed lane will remain open to traffic across the new bridge, and the southbound travel lane will remain closed. The Exit 185 southbound off-ramp will reopen. The southbound on-ramp may close, if necessary, while crews complete excavation, milling, and paving at the south end of the travel lane and ramp.
- Phase 4: The southbound travel lane will be opened to traffic across the new bridge. The southbound high-speed lane and off-ramp will remain open, and the southbound on-ramp will be opened.
During the Exit 185 southbound off-ramp closure, motorists should use Exit 186 for Stillwater Avenue. Drivers should then follow detour signs directing vehicles down Stillwater Avenue to Broadway. During the Exit 185 southbound on-ramp closure, motorists should follow detour signs directing vehicles down Broadway to Stillwater Avenue to access I-95 at Exit 186. Message boards will be in place alerting drivers of the upcoming closures.
MaineDOT appreciates the public’s patience and cooperation as crews complete this important infrastructure improvement.
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.